Actual operation of overhead power line structures at stages of the life cycle

https://doi.org/10.22227/2305-5502.2026.1.5

Abstract

Introduction. The object of the study is the structures of overhead power lines (OPL), including their foundations; the subject is the actual performance of these structures (APS) at the various stages of the OPL life cycle (LC) (construction, operation and reconstruction), as a linear structure, which determines the practical significance of this paper. The aim is determined by the need to ensure the required regulatory reliability of OPL operation. The objectives of the study are to investigate the factors affecting the actual performance of OPL at the various stages of their life cycle.

Materials and methods. The actual operation of overhead line structures, as a set of real deviations of the characteristics of the elements from the standard values, is defined in the form of specific factors. The factor of emergency damage to structures, including the collapse of poles, is also included in the actual operation of structures. After repair or reconstruction, such as the replacement of damaged and collapsed poles or the replacement of old wires with new innovative wires, the operation continues as part of the life cycle.

Results. This is a real example of the successful reconstruction of a 220 kV overhead line, where the wires were replaced with new innovative wires with a gap, which allow the current-carrying part to move relative to the supporting core under high-temperature deformations. This reconstruction is possible due to the increased strength and reduced diameter of the new wire with a compact cross-section. This allowed the new innovative wires and lightning rods to be hung on old poles with reinforced foundations, significantly reducing the cost of the overhead line reconstruction.

Conclusions. This approach allowed the use of old poles for suspending new wires and a lightning protection cable. As a result, the capacity of the 220 kV overhead line increased by 60 % or more. The life cycle is represented by a new graphical model, the “life curve”, which shows the change in the failure rate ω over time τThe curve consists of three main stages: break-in, normal operation, and wear. This graph is proposed to describe the process of subsequent reconstruction as the fourth main stage, with an extended time axis as part of the new life cycle of the overhead line.

About the Author

N. A. Senkin
Saint Petersburg State University of Architecture and Civil Engineering (SPbGASU); Rosseti Scientific and Technical Center
Russian Federation

Nikolai A. Senkin — Candidate of Technical Sciences, Associate Professor, Associate Professor of the Department of Metal and Wooden Structures; chief expert

4, 2nd Krasnoarmeyskaya st., Saint Petersburg, 190005;
build. 3, 22 Kashirskoye shosse, Moscow, 115201

Scopus: 57302511900, ResearcherID: IWL-9658-2023



References

1. Senkin N.A. Building structures of overhead power transmission lines 110–750 kV: life cycle stages of the report. Actual problems of computer modeling of structures and structures : abstracts of reports of the VIII international symposium. 2003; 253-254. EDN GKTMFS. (rus.).

2. Senkin N., Belyakova T., Malchikov D., Vasilyev V. The actual operation of steel structures of overhead power lines with a voltage of 35 kV and above. Metall Constructions. 2022; 28(1):5-18. EDN FEJAMT. (rus.).

3. Sanzharovskiy R.S., Astafeev D.O., Ulitskiy V.M., Zyber F. Reinforcement during the reconstruction of buildings and structures. The design and calculations of reinforcement of buildings during reconstruction. St. Petersburg, SPbGASU, 1988; 637. (rus.).

4. Gorokhov Ye., Smirnova N., Shelikhova H. Control system for reconstruction of overhead line supports taking into account the requirements of operation and reliability of power supply to consumers. Metall Constructions. 2023; 29(1):33-45. EDN SOQPTO. (rus.).

5. Gorokhov Ye., Smirnova N., Orzhekhovsky A. Analysis of the survivability of the 220 kV anchor-angular support structure with imperfections under the action of static loads. Metall Constructions. 2023; 29(4):209-219. EDN JCQXPU. (rus.).

6. Khalyasmaa A.I., Eroshenko S.A., Bogdanov D. Adaptive life-cycle control system for overhead transmission lines using forecasting models. 2017 8th IEEE International Conference on Software Engineering and Service Science (ICSESS). 2017; 75-78. DOI: 10.1109/ICSESS.2017.8342867

7. Gan J., Li L. Research on the Technical Reliability of the Overhead Transmission Lines Based on the Life Cycle Technology. IOP Conference Series: Earth and Environmental Science. 2020; 558(5):052037. DOI: 10.1088/1755-1315/558/5/052037

8. Brennan G. Refurbishment of Existing Overhead Transmission Lines. CIGRE. B2-203. 2004; 9.

9. Kuryanov V.N., Sultanov M.M., Fokin V.A., Timashova L.V. Innovative high-efficiency wires for power transmission lines. Energy of Unified Grid. 2016; 4(27):70-78. EDN WIDLMX. (rus.).

10. Senkin N.A. Actual tasks in the design and construction of the UNES overhead line: wire, cables, fittings. Energoexpert. 2014; 1(42):72-79. (rus.).

11. Trull V.A., Senkin N.A. Research of the Influence of Foundation Displacements on the Forces in the Rods of Tower-Type Structures. Metal Structures and Testing of Structures: Interuniversity Thematic Collection of Papers. 1980; 25-32. (rus.).

12. Semashkin A.D., Tusnin A.R., Berger M.P. Methods of structural analysis for resistance to progressive collapse. Construction: Science and Education. 2023; 13(2):31-50. DOI: 10.22227/2305-5502.2023.2.3. EDN SSKMDG. (rus.).

13. Kolchunov V.I., Iliushchenko T.A., Fedorova N.V., Savin S.Y., Tur V.V., Lizahub A.Al. Structural robustness : an analytical review. Building and Reconstruction. 2024; 3(113):31-71. DOI: 10.33979/2073-7416-2024-113-3-31-71. EDN FHLGWH. (rus.).

14. Fedorova N.V., Savin S.Yu. Progressive collapse resistance of facilities experienced to localized structural damage : an analytical review. Building and Reconstruction. 2021; 95(3):76-108. DOI: 10.33979/2073-7416-2021-95-3-76-108. EDN FMVVRU.

15. Androsova N.B., Vetrova O.A. The analysis of studies and requirements for the protection of buildings and structures against progressive collapse in regulatory documents of Russia and the European union. Building and Reconstruction. 2019; 1(81):85-96. DOI: 10.33979/2073-7416-2019-81-1-85-96. EDN ZCKBDF. (rus.).

16. Senkin N.A. Progressive collapse and restoration of overhead power lines structures. News of Higher Educational Institutions. Construction. 2023; 10(778):5-20. DOI: 10.32683/0536-1052-2023-778-10-5-20. EDN VIILKZ. (rus.).

17. Tanasoglo A.V., Garanzha I.M., Orzhekhov-skyi A.N., Pisareva M.M. Structural form improvement of steel narrow-based lattice supports for high-reliability overhead lines. Construction: Science and Education. 2025; 15(2):20-39. DOI: 10.22227/2305-5502.2025.2.2. EDN CSFUUW. (rus.).

18. Kryukov K.P., Novgorodtsev B.P. Constructions and mechanical calculation of electric transmission lines. Leningrad, Energiya, 1979; 312. (rus.).

19. Yakovlev L.V., Kaverina R.S., Dubinich L.A. A set of works and proposals to im-prove overhead line reliability at the design and operation stage. Power transmission lines 2008: design, construction, operational experience and NTP. 2008; 28-49. (rus.).

20. Krylov S.V. Technical condition of overhead lines of 35 kV and above: methods of investigation. Electrical Engineering News. 2006; 1(37):35-41. (rus.).

21. Yefimov E.N., Timashova L.V., Yasinskaya N.V. Causes and nature of damage to components of overhead power transmission lines with a voltage of 110–750 kV in 1997–2007. Energy of Unified Grid. 2012; 5(5):32-41. EDN VXCBYN. (rus.).

22. Galiaskarov I. On reliability characteristics and service time limits of 500 kV overhead lines. E3S Web of Conferences. 2020; 216:01014. DOI: 10.1051/e3sconf/202021601014

23. Gorokhov E.V., Shapovalov S.M., Udod E.I. et al. Improving the reliability and durability of electric grid structures. Kyiv, Tekhnika, 1997; 283. (rus.).

24. Gorokhov Ye.V., Bakayev S.M., Nazim Ya.V., Morgay V.V., Popov M.S. Failure cause and consequence analysis at the high voltage (330 kV) line sections of the Dzhankoy local electrical power station of the Crimean electrical power system of the NEC “UKRENERGO”. Metall Constructions. 2010; 16(2):75-92. EDN MUVVGJ. (rus.).

25. Bakayev S., Smirnova N., Morgay V. Reliability growth of operation of overhead transmission lines (set of works and suggestion according to acting opl). Metall Constructions. 2015; 21(3):147-165. EDN VAAUIP. (rus.).

26. Tanasoglo A., Fomenko S., Bakayev S., Kozlova L. Determination of reduced tension at conductive wires and lightning protection cables breakage of overhead power lines with a voltage of 35–110 kV. Metall Constructions. 2022; 28(4):195-205. EDN EOCYGC. (rus.).

27. Senkin N.A., Filimonov A.S. Interaction of structural elements in the overhead transmission power line due to the falling tower. Structural Mechanics and Analysis of Constructions. 2024; 6(317):27-34. DOI: 10.37538/0039-2383.2024.6.27.34. EDN ITCRDE. (rus.).

28. Belyakova T.E. Influence of manufacturing and assembly accuracy on the loadbearing capacity of intermediate overhead line supports. Series “Construction” : collection of articles by undergraduates and postgraduates. 2022; 3-11. EDN WHUCGL. (rus.).

29. Senkin N.A., Vasilev V.S. Actual operation of structures: the interaction of structures and the soil base of lattice supports of overhead power lines. Vestnik MGSU [Monthly Journal on Construction and Architecture]. 2025; 20(5):637-654. DOI: 10.22227/1997-0935.2025.5.637-654. EDN HXICYU. (rus.).

30. Romanov P.I., Kachanovskaya L.I., Chernova T.V. On the issue of increasing the corrosion resistance of over-head line supports. Progressive solutions in electric grid construction : collection of scientific papers. Moscow, 1986; 146-152. (rus.).

31. Romanov P.I., Kachanovskaya L.I., Chernova T.V. Control of corrosion defects of metal elements of overhead line supports. Progressive solutions in electric grid construction : collection of scientific papers. 1986; 40-48. (rus.).

32. Senkin N. Improvement of Methods of Inspection of Steel Structures of Overhead Power Line. Lecture Notes in Civil Engineering. 2022; 155-163. DOI: 10.1007/978-3-031-30570-2_14

33. Gusakova E., Ovchinnikov A., Volkov A. Approaches to the structuring of the information model of the life cycle stages of a construction object. E3S Web of Conferences. 2019; 97:01002. DOI: 10.1051/e3sconf/20199701002


Review

For citations:


Senkin N.A. Actual operation of overhead power line structures at stages of the life cycle. Construction: Science and Education. 2026;16(1):72-91. (In Russ.) https://doi.org/10.22227/2305-5502.2026.1.5