Variability of work overlap during capital repair of buildings
https://doi.org/10.22227/2305-5502.2026.1.8
Abstract
Introduction. Capital repair of buildings is a comprehensive process that encompasses a wide range of building maintenance and construction processes. To achieve maximum efficiency, it is crucial to properly plan and manage resources, taking into account the specifics of objects, conditions, and characteristics of work performed. It is necessary to study and implement methods for combining operations that allow reducing the duration of capital repairs and lowering costs in construction and maintenance production.
Materials and methods. In this research, modern approaches to designing organizational and technological models for capital repair production were utilized. Algorithms for calculating parameters such as resource consumption intensity, task execution duration, and interprocess connection conditions were developed. Special attention was given to methodologies for assessing organizational downtimes and modules enabling efficient distribution of labour and material resources.
Results. The proposed methodologies enable optimization of capital repair processes through rational allocation of resources and overlapping of works. The use of combined flows for roofing, facade renovation, and engineering systems installation in multi-apartment residential buildings demonstrated significant reduction in total repair time without compromising the quality of executed works. Developed algorithms provide computational justification for selecting an optimal method of performing tasks.
Conclusions. The conducted research confirmed the significance of variability in overlapping works during the capital repair of buildings. Proposed algorithms and techniques make it possible to significantly reduce both the time required for completion and the cost of the works.
About the Authors
E. A. KorolRussian Federation
Elena A. Korol — Doctor of Technical Sciences, Professor, Professor of the Department of Housing and Public Utilities; chief research fellow
26 Yaroslavskoe shosse, Moscow, 129337;
21 Lokomotivny proezd, Moscow, 127238
A. G. Gudkova
Russian Federation
Anna G. Gudkova — Candidate of Technical Sciences, Senior Lecturer of the Department of Housing and Public Utilities; senior researcher
26 Yaroslavskoe shosse, Moscow, 129337;
21 Lokomotivny proezd, Moscow, 127238
R. S. Petrosyan
Russian Federation
Rima S. Petrosyan — Candidate of Technical Sciences, Associate Professor of the Department of Technology and Organization of Construction Production; senior researcher
26 Yaroslavskoe shosse, Moscow, 129337;
21 Lokomotivny proezd, Moscow, 127238
D. D. Antoniadi
Russian Federation
Diana D. Antoniadi — postgraduate student of the Department of Housing and Public Utilities
26 Yaroslavskoe shosse, Moscow, 129337
References
1. Grabovoi K.P., Korol O.A. Analysis of trends and reserves for increasing the economic efficiency of energy-saving measures in the construction industry and housing and communal services. Innovative technical solutions for environmental sustainability in construction and management of urban housing and communal services: collection of materials of the VI International scientific and practical conference. 2014; 65-71. EDN UIRGCL. (rus.).
2. Grabovoi K.P. Features of conducting construction and technical research of construction, reconstruction, modernization, technical re-equipment and major repairs projects implemented using targeted budgetary funds in arbitration proceedings. Actual problems of the construction industry and education: collection of reports of the First National Conference. 2020; 1019-1022. EDN INPKYU. (rus.).
3. Korol E.A., Antoniad D.D., Myanyamsheva V.D. Organizational and technological measures to improve the manufacturability of roofing and facade work during major repairs of buildings. BST: Bulletin of Construction Technology. 2025; 5(1089):26-29. EDN AOPNYK. (rus.).
4. Korol O., Dehtyar' E., Petrov A. Improving the calendar planning of capital repairs of buildings, taking into account the forecast of consumption and prolongation of the service life of thermal insulation materials. Construction and Architecture. 2022; 10(4):46-50. DOI: 10.29039/2308-0191-2022-10-4-46-50. EDN PDSLJF. (rus.).
5. Korol O.A. Conceptual foundations of the regulatory framework of capital repairs of common property in apartment houses. BTS: Bulletin of Construction Technique. 2018; 11(1011):20-21. EDN YMXDPF. (rus.).
6. Kuzmina T.K., Babushkina D.D. Systematization of criteria for determining the priority of major repairs of common property in apartment buildings. Engineering journal of Don. 2023; 9(105):405-416. EDN IBGJJQ. (rus.).
7. Kuzmina T.K., Babushkina D.D., Fedorova U.A., Kasyanov D.S., Sukhorukov A.E. Analysis of design documentation development timelines for structural components in capital repairs projects. Construction Production. 2025; 2:132-140. DOI: 10.54950/26585340_2025_2_132. EDN DDMZLJ. (rus.).
8. Lapidus A.A., Bidor T.Kh., Khubaev A.O., Ekba S.I. Organizational and Technological Decisions for Renovation and Major Repair of Buildings and Structures. Moscow, MGSTU, 2024; 64. EDN KTDCBD. (rus.).
9. Lapidus A.A., Bidov T.Kh., Khubaev A.O. Study of organizational and technical solutions when carrying out major repairs of multiapartment residential buildings. Izvestiya Tula State University. Technical sciences. 2024; 2:172-176. DOI: 10.24412/2071-6168-2024-2-172-173. EDN UBHFXR. (rus.).
10. Plotnikov A.D., Korol O.A. Monitoring of the operational quality of work on major repairs of apartment buildings. BST: Bulletin of Construction Technology. 2025; 7(1091):60-64. EDN BBBHBE. (rus.).
11. Kagazezhev A.Yu., Fatullaev R.S., Khubaev A.O., Shesterikova Ya.V. The analysis of the main problems in planning of overhaul programs. Science Prospects. 2022; 12(159):81-86. EDN WWCYKN. (rus.).
12. Mailyan L.D., Sizen N.O. Organizational and technological level of major repairs of buildings and structures. The Russian Automobile and Highway Industry Journal. 2025; 22(1):(101):136-147. DOI: 10.26518/2071-7296-2025-22-1-136-147. EDN BPZQQG. (rus.).
13. Seleznev A.B., Trusov K.S. Increasing energy efficiency during major repairs of multi-apartment buildings in the Russian Federation: methods and technologies. Applied Economic Research. 2024; 3:50-57. DOI: 10.47576/2949-1908.2024.3.3.005. EDN TOTTAK. (rus.).
14. Vekshin I.A., Kurakova O.A. Application of innovative technologies and materials in routine and major repairs of apartment buildings. Economy and Entrepreneurship. 2024; 9(170):1297-1302. DOI: 10.34925/EIP.2024.170.9.240. EDN KUZFLG. (rus.).
15. Fatullaev R.S., Borovkova A.E., Sharovatov N.A., Loguzov V.A. The main factors affecting labor productivity in the performance of capital repairs in apartment buildings. Science and Business: Ways of Development. 2024; 7(157):58-64. EDN JRLPTF. (rus.).
16. Korol E.A., Petrosyan R.S. Methodological Approaches to the Formation of the Organizational and Technological Mechanism for Improving the Manufacturability of Work during the Overhaul of Buildings. IOP Conference Series: Materials Science and Engineering. 2020; 753(3):032057. DOI: 10.1088/1757-899X/753/3/032057. EDN SJIOGW.
17. Wong S.K., Chau K.W., Yau Y., Cheung A.K.C. Property price gradients: the vertical dimension. Journal of Housing and the Built Environment. 2011; 26(1):33-45. DOI: 10.1007/s10901-010-9203-8. EDN ZGLNTC.
18. Glass Ja., Bygballe L.E., Hall D. Transforming construction: the multi-scale challenges of changing and innovating in construction. Construction Management & Economics. 2022; 40(11-12):855-864. DOI: 10.1080/01446193.2022.2141432. EDN WMTXIL.
19. Dou Yu., Yan X., Li T., Wang M., Zheng R., Yuan Y. Quality and safety management framework for intelligent construction: Cases study in China. KSCE Journal of Civil Engineering. 2025; 29(4):100068. DOI: 10.1016/j.kscej.2024.100068. EDN QWVZMC.
20. Razali M.F., Haron N.A., Hassim S., Alias A.H., Harun A.N., Abubakar A.S. A Review: Application of Building Information Modelling (BIM) over Building Life Cycles. IOP Conference Series: Earth and Environmental Science. 2019; 357(1):012028. DOI: 10.1088/1755-1315/357/1/012028
21. Yin X., Liu H., Chen Y., Al-Hussein M. Building information modelling for off-site construction: Review and future directions. Automation in Construction. 2019; 101:72-91. DOI: 10.1016/j.autcon.2019.01.010
22. Jaśkowski P., Biruk S., Krzemiński M. Modeling the problem of sequencing projects in the contractor’s portfolio of orders. Archives of Civil Engineering. 2022; 68(3):307-322. DOI: 10.24425/ace.2022.141887
Review
For citations:
Korol E.A., Gudkova A.G., Petrosyan R.S., Antoniadi D.D. Variability of work overlap during capital repair of buildings. Construction: Science and Education. 2026;16(1):126-137. (In Russ.) https://doi.org/10.22227/2305-5502.2026.1.8
JATS XML